查看完整案例
收藏
下载
翻译
Architects:SALT Architects
Area:3470m²
Year:2022
Photographs:Southland Photography
Project Managers:Water & Wastewater Engineering
Civil Engineers:Water & Wastewater Engineering
Mechanical & Electrical Engineers:JGP Group
Structural Engineering:WA Structural Design
Building Contractor:Hiload Inyanga Construction
Bulk Earthworks Contractor:Amadla Construction
City:Cape Town
Country:South Africa
Text description provided by the architects. The project is a new Blower House Complex on the Athlone Wastewater Treatment Works just outside Cape Town. On the Ground floor, the complex consists of a large blower room with its Motor Control Centre (MCC room) and air plenums, an MCC for the future upgrade’s reactors, locker rooms for the ground staff, a laundry room, and stores.
The nature of the first floor is more clerical and includes the control room, SCADA station, offices, boardroom, laboratory, and staff amenities.
Connected at an angle to the blower house is the new electrical building which houses four large diesel generators and their associated plant to run the whole plant in case of a power outage.
Project gallery
Project location
Address:Cape Town, South Africa